NSIP tracker

Major energy infrastructure consents across Great Britain.

Nationally significant infrastructure projects in England and Wales under the Planning Act 2008, and their Scottish equivalents under sections 36 and 37 of the Electricity Act 1989 — with stage, key dates and, for NSIPs, the statutory deadlines that follow.

England and Wales: snapshot of the Planning Inspectorate register of applications taken 12 November 2026.

Always confirm against the live project page before relying on a date.

Filter projects

    How the stages and dates are worked out

    England and Wales (Planning Act 2008)

    • Acceptance: the Planning Inspectorate has 28 days from receipt to decide whether to accept an application.
    • Examination: must close within six months of starting. Where the Examining Authority has published an anticipated close date, that date is used.
    • Recommendation: due to the Secretary of State within three months of the examination closing.
    • Decision: due within three months of the recommendation. The Secretary of State can extend this deadline by written statement to Parliament.

    Scotland (Electricity Act 1989)

    • Stages are those shown on the Energy Consents Unit case search. There is no statutory examination timetable equivalent to the Planning Act 2008, so no deadlines are calculated.
    • “Public inquiry (DPEA)” means the case has been referred to the Planning and Environmental Appeals Division. From 18 February 2026, a planning authority objection no longer makes an inquiry mandatory.
    • Section 36 covers generating stations over 50MW; section 37 covers overhead lines.